A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task? |
| A. | 4(2/3) days |
| B. | 4 days |
| C. | 5(1/3) days |
| D. | 1(1/3) days |
| Answer» D. 1(1/3) days | |