| 1. |
A and B together can do a piece of work in 6 days. If A can alone do the work in 18 days, then the number of days required for B to finish the work is |
| A. | 12 |
| B. | 15 |
| C. | 9 |
| D. | 10 |
| Answer» D. 10 | |