A and B together can complete a piece of work in 4 days if A alone can complete the same work in 12 days, in how many days can B will alone complete that work? |
| A. | 4 Days |
| B. | 6 Days |
| C. | 10 Days |
| D. | 2 Days |
| Answer» C. 10 Days | |