A and B can together complete a task in 16 days. They started a task together and after 4 days A leave, B takes 24 days to finish the rest of the task. How many days would B have taken to do the task if he worked alone? |
| A. | 30 days |
| B. | 24 days |
| C. | 32 days |
| D. | 34 days |
| Answer» D. 34 days | |