| 1. |
A and B can separately complete a piece of work in 20 days and 30 days respectively. They worked together for some time then B left the work. If A completed the rest of the work in 10 days, then B worked for how many days? |
| A. | 6 days |
| B. | 8 days |
| C. | 12 days |
| D. | 16 days |
| Answer» B. 8 days | |