| 1. |
A and B can do a work in 21 days, A is 7/4 times as efficient as B. In how many days, A alone can complete the 100/3% of the work? |
| A. | 13 |
| B. | 17 |
| C. | 22 |
| D. | 11 |
| Answer» E. | |