A and B can do a work in 12 days, B and C in 15 days, C and A in 20 days. If A, B and C work together, they will complete the work in: |
| A. | 5 days |
| B. | 7 days |
| C. | 10 days |
| D. | 12 days |
| Answer» D. 12 days | |