'A' and ' B ' can do a piece of work in 25 days and 30 days respectively. Both start the work together but 'A' leaves the work 8 days before its completion. Find the time in which the work is finished |
| A. | 18 days |
| B. | 21 days |
| C. | 25 days |
| D. | 27 days |
| Answer» B. 21 days | |