| 1. |
A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last? |
| A. | 6 days |
| B. | 10 days |
| C. | 15 days |
| D. | 20 days |
| Answer» C. 15 days | |