A and B can do a piece of work in 10 days and 15 days, respectively. They work together for 4 days. The remaining work is completed by C alone in 12 days. C alone will complete \(\frac{4}{9}\) part of the original work in: |
| A. | 24 days |
| B. | 12 days |
| C. | 20 days |
| D. | 16 days |
| Answer» E. | |