A and B can do a given piece of work in 8 days, B and C can do the same work in 12 days and A,B,C completer it in 6 days, Number of days required to finish the work by A and C is |
| A. | 8 |
| B. | 24 |
| C. | 12 |
| D. | 16 |
| Answer» B. 24 | |