A and B can complete a work together in 12 days. A alone can complete same work in 18 days. A and B started doing work and after 4 days A left. In how many days remaining work will be completed by B? |
| A. | 12 days |
| B. | 24 days |
| C. | 36 days |
| D. | 18 days |
| Answer» C. 36 days | |