A and B can complete a work in 36 days. However, A had to leave a few days before the work was completed and hence it took 54 days to complete the work. If A alone can complete a work in 48 days, then how many days before the completion of the work did A take leave? |
| A. | 24 |
| B. | 30 |
| C. | 25 |
| D. | 28 |
| Answer» B. 30 | |