MCQOPTIONS
Saved Bookmarks
| 1. |
A alone can complete a work in 14 days and B alone can complete the same work in 21 days. A and B start the work together but A leaves the work after 4 days of the starting of work. In how many days B will complete the remaining work? |
| A. | 9 days |
| B. | 16 days |
| C. | 12 days |
| D. | 11 days |
| Answer» E. | |