MCQOPTIONS
Saved Bookmarks
| 1. |
6 workers complete a job in 8 days. How Br many workers are needed to complete the job 2 days in advance? |
| A. | \[4\] |
| B. | \[8\] |
| C. | \[10\] |
| D. | \[6\] |
| Answer» C. \[10\] | |