45 men complete a piece of work in 30 days working 12 hours a day. In how many days will 60 men complete that work working 10 hours a day ? |
| A. | 27 days |
| B. | 30 days |
| C. | 33 days |
| D. | 35 days |
| Answer» B. 30 days | |