MCQOPTIONS
Saved Bookmarks
| 1. |
40 men working 8 hours per day can complete a piece of work in 21 days. How many hours per day must 120 men work to complete the same piece of work in 7 days? |
| A. | 9 hrs |
| B. | 10 hrs |
| C. | 12 hrs |
| D. | 8 hrs |
| Answer» E. | |