40 men can complete a piece of work in 18 days. Eight days after they started working together, 10 more men joined them. How many days will they now take to complete the remaining work ? |
| A. | days |
| B. | days |
| C. | 0 days |
| D. | 2 days |
| Answer» C. 0 days | |