25 men can complete a task in 16 days. Four days after they started working, 5 more men, with equal workmanship, joined them. How many days will be needed by all to complete the remaining task? |
| A. | 15 days |
| B. | 18 days |
| C. | 12 days |
| D. | 10 days |
| Answer» E. | |