18 people could complete the task in 12 days. After 4 days of work, 2 of the workers left. How many days from the time the worker left will it take to complete the task now? |
| A. | 6 |
| B. | 9 |
| C. | 10 |
| D. | 8 |
| Answer» C. 10 | |