| 1. |
16 workers working 8 hours per day can demolish a building in 32 days. In how many days 24 workers working 12 hours per day can demolish the same building? |
| A. | 128/3 days |
| B. | 56/3 days |
| C. | 128/9 days |
| D. | 56/9 days |
| Answer» D. 56/9 days | |