16 persons working 6 hours a day can complete a work in 10 days. In how many days 24 persons working 8 hours a day will complete 80% of that work? |
| A. | 8 |
| B. | 4 |
| C. | 3 |
| D. | 6 |
| Answer» C. 3 | |